Chetek Long Bridge Construction: What County D Drivers Should Know

"Carrying out a final project plan shaped directly by local public input." That's how the Chetek Alert described the County Highway D rehabilitation on Long Bridge when work started Aug. 3. Almost three months later, the temporary signals at each end of the bridge are still running. The schedule has also moved. Every source published around the start date gave late October as the finish. The Wisconsin Department of Transportation now lists the job as running "Aug. 3 through late November."

The one-lane signals are the outcome Chetek asked for. In 2024 the community pushed back on a plan that would have shut the bridge entirely. What it won was one open lane and a later start. The price of that deal was a longer construction season, and it has turned out longer still.

The plan that would have closed Long Bridge

When WisDOT first released plans in August 2024, the bridge was supposed to close completely starting around Memorial Day. According to the Chetek Alert's reporting, traffic would have gone on an 18-mile detour over County Highway M, U.S. Highway 8 and County Highway SS. That would have added up to 20 minutes to a daily commute and more than 30 minutes to emergency response times.

That detour is the one you may still remember. WisDOT's own project page still carries traffic language describing a full closure and detour. The plan that actually got built is different. The WisDOT Northwest Region weekly update says County D "remains open to a single lane of traffic at the bridge controlled by temporary traffic signals."

Two changes came out of a well-attended virtual public hearing in late 2024. The Chetek Alert reported both:

  • One lane stays open. Chetek Fire Department Chief Ryan Olson and Police Chief Ron Ambrozaitis warned that half-hour emergency delays would be unacceptable. WisDOT agreed to keep one lane open, with temporary signals on both sides of the bridge, for the whole project.
  • Work waits until August. Local resort owners, restaurateurs and the Chetek Chamber of Commerce warned that closing the bridge all summer would hurt local businesses. Barron County Highway Commissioner Mark Servi formally asked WisDOT to hold off until August, after peak tourist traffic and events like Liberty Fest. WisDOT adopted the August start.

The emergency concern stayed part of the final plan. The Alert reported that first responders would coordinate with construction crews to get priority passage through the work zone during calls.

The trade built into the compromise

Keeping one lane open was never going to be free. The Chetek Alert reported that the single-lane setup stretched the estimated construction time to 60 to 75 calendar days. Officials agreed that cost was worth it to protect safety, school bus routes and local business.

Counting from Aug. 3, 75 days lands in mid-October. The public finish date was a little later. WisDOT's July 28 contract announcement projected completion in late October, and WEAU repeated that date on Aug. 2. WisDOT's Sept. 18 Northwest Region update moved the end date to late November, and the current weekly update shows the same schedule.

The cost estimate has grown too. In August 2024, WisDOT put the project at $750,000 to $999,000. The contract Gov. Tony Evers signed with Lunda Construction Co. of Black River Falls came in at $2.39 million.

Here's the timeline, start to finish:

  1. 1973. Long Bridge is built. It connects Sumner Avenue to County Highway D across Lake Chetek.
  2. 1991. The deck gets its last overlay.
  3. August 2024. WisDOT proposes a full closure starting around Memorial Day, with the 18-mile detour.
  4. Late 2024. At a virtual public hearing, local leaders push for one open lane and an August start.
  5. July 28, 2026. WisDOT announces the contract and projects a late-October finish.
  6. Aug. 3, 2026. Single-lane traffic under signals begins.
  7. Sept. 18, 2026. WisDOT moves the schedule to "through late November."

What the crews are actually doing out there

The signals have been up long enough that the work behind them can blur into general construction. The project list is specific, though. The Chetek Alert reported that the bridge still has an overall satisfactory structural rating, but it shows clear concrete wear across the deck, piers, abutments, parapets and sidewalk curbs. The scope WisDOT published covers:

  • A 1.5-inch concrete overlay on the bridge deck, the first new overlay since 1991
  • Repairs to the concrete sidewalk, bridge piers and parapet
  • Joint repairs and cleaning of the drainage grates
  • Painting the bridge girders
  • Milling 2 inches of old asphalt on both sides of the bridge and paving 2 inches of new hot-mix asphalt
  • Replacing curb, gutter and sidewalk
  • Restoring the landscaping around the work site

WisDOT hasn't published dates for each of these phases or a percent-complete figure. The weekly update lists the full scope and the late-November schedule, and that's all. The weekly construction page is still the best place to check the current status before a trip that depends on timing.

WEAU also reminded drivers that using a handheld cell phone in a Wisconsin work zone is illegal.

On foot and on the water

The plan also covers people who aren't driving. The Chetek Alert reported that temporary pedestrian accommodations would be provided across the bridge for the whole project. Boaters keep access under the bridge, which WEAU also confirmed. There's one caveat on the water side. A WisDOT representative told the Alert that if crews find spots needing full-depth repairs, boat access could be limited for safety while that work is done.

That caveat matters less every week as boats come off the chain for the season. But anyone still running a boat under the bridge in late fall should know it's possible.

Fall's downtown calendar runs inside the signal window

The August start protected Liberty Fest. With a late-November finish, Chetek's fall events fall during the single-lane period instead, and the first holiday events come right after it. Here's what the Chetek Area Chamber of Commerce calendar lists for the weeks ahead:

Date Event Where and when
Fri., Oct. 30 Witches Brew & Warlocks Too Beer Crawl Chetek-area businesses, 11 a.m. to 7 p.m., with samples and extended downtown dining and shopping hours
Sat., Oct. 31 Chetek Lions Club Halloween Party Chetek-Weyerhaeuser High School, 1001 Knapp St., 6 to 9 p.m.
Sat., Nov. 28 Small Business Saturday Chetek-area shops and restaurants
Fri., Dec. 4 Chetek Lions Club Christmas for Kids auction Gilligans, 2542 8 1/4 Ave., 6 to 10 p.m.
Sat., Dec. 5 Santa's Arrival & Family Fun Day The Chetek Center on 1st Avenue, 2 to 7 p.m., with a 5:30 p.m. tree lighting and Christmas Parade of Lights at Main St. Park

The beer crawl and the Lions Halloween Party both fall well inside the current schedule. Small Business Saturday lands right at "late November," so whether the signals are still up that day depends on how the last weeks of work go. The December events are past the posted window, but the Chamber's listing for Santa's Arrival notes that its times may change too.

For donations to the Christmas for Kids auction, the Lions Club listing says items can be dropped off at Indianhead Insurance Agency on Knapp Street.

A note on names

The bridge goes by several names, which can confuse anyone checking the schedule. WisDOT calls it the Lake Chetek Bridge on County D. Its project page calls the road Sumner Avenue, and local coverage uses Sumner Avenue too. The Chetek Alert says it's known locally as Long Bridge. The City of Chetek's parks listings place Long Bridge Park at County M and County D, with a public dock at 100 Sumner Ave. When you're scanning the WisDOT weekly page, look under Barron County for "County D, Lake Chetek Bridge in Chetek."

Thanks to the 2024 hearing, Chetek kept its main crossing open all summer without the 18-mile detour, and the trade was a few extra weeks of red lights this fall. If you're planning to list or tour a home on either side of Long Bridge before the signals come down, I'm glad to help you plan showings and travel times around the work zone. Hantke Homes is a phone call away. Schedule your free consultation.